Steps in the process of building a photovoltaic system
1. Solar-energy audit, which includes:
- Examining the terrain on which is projected to be implemented project-slope, exhibition, etc.
- Determining the level of solar radiation
- Forecast annual production of energy
- Proposal for a specific technology to be used for implementation of the system
2.Registration of a Company
3. Purchase of land or the establishment of real rights (right of building)
4. Preparation of a detailed structural plan
5. Changing the status of the land if necessary
6. Obtaining visas for design by the municipality
7. Tabled a request to examine the conditions for accession to power distribution system in the respective electric company
8. Conclusion of a preliminary contract with the local electric company
9. Investment project
10. Get a building permit from the local authority
11. Conclusion of a final treaty of accession to power network with relevant electric company
12. Preparation of project documents Business Plan and Application form in measure 312
13. Application and signing of contract to finance the project
14. Supply, construction / installation of electric system
15. 72 hours testing
16. Obtaining permission to use (Act 16)
17. A contract for network access
18. A contract for the purchase of electric energy
|